Construction Updates

1st January 2024 Report

1. Block 
– All Floors completed
2. Clubhouse
– Air Condition work in progress.

1st December 2023 Report

1. Block 
– All Floors completed
2. Clubhouse
– Air Condition work in progress.

1st November 2023 Report

1. Block 
– 24th Floor Pour-2 work in progress.
2. Clubhouse
– Ready for Fire Fighting and Air conditioning.

1st October 2023 Report

1. Block 
– 23rd floor pour-1 slab Reinforcement work in progress, Pour-2 slab shuttering work in progress.
2. Clubhouse
– Ready for Fire Fighting and Air condition.

1st September 2023 Report

1. Block 
– 21st floor pour-1 slab concrete work in progress, Pour-2 wall Reinforcement work in progress.
2. Clubhouse
– Ready for Fire Fighting and Air condition.

1st August 2023 Report

1. Block 
– 19th floor pour-1 completed, Pour-2 slab concrete work in progress.
2. Clubhouse
– Internal screed work in progress.

1st July 2023 Report

1. Block 
– 18th floor pour-1 completed, Pour-2 ready for slab concrete.
2. Clubhouse
– Internal walls finishing work in progress.

1st June 2023 Report

1. Block 
– 16th floor pour-1 wall reinforcement in progress, Pour-2 ready for casting.
2. Clubhouse
– Internal works in progress.

1st May 2023 Report

1. Block 
– 14th floor pour-1 slab reinforcement in progress, Pour-2 ready for casting.
2. Clubhouse
– Internal brick work in progress.

1st Apr 2023 Report

1. Block 
– 12th floor pour-1 completed, Pour-2 ready for casting.
2. Clubhouse
– Internal brick work in progress.

1st Mar 2023 Report

1. Block 
– 08th Floor slab completed, 09th floor Reinforcement in progress.
2. Clubhouse
–  Brick work in progress.

1st Oct 2022 Report

Particulars Location Work Status
BASEMENTS Basement -1 100% completed
Basement -2 100% completed
Basement -3 100% completed
CLUB HOUSE Ground Floor slab 100% completed
First Floor slab 100% completed
RESIDENTIAL ZONE – 2nd Floor Slab Flat 1 & 2 shear wall activities in progress